Learn moreYunnan Yunpeng Hydropower Project
Technology
Hydro
Renewables

Country
China
Asia

Standard
CDM
Compliance
Stage
Issuance
2013-03-19
Awaiting scheduling
Total issued
1,064,780
tCO2
Annual Reduction
700,009
tCO2/year
CDM
Scope
| Energy industries |
Additionality
| Tool version : | 5.2 |
| Barrier analysis: | no |
| Investment analysis : | -Benchmark Analysis |
Provider ID
| UNEP | cdm4406 |
| UNFCCC | 2580 |
| Methodology | Ver | Description |
| ACM0002 | 7 | Grid-connected electricity generation for renewable sources (no biomass) |
| ACM0002 | 7 | Grid-connected electricity generation for renewable sources (no biomass) |
Description
The Yunnan Yunpeng Hydropower Project (hereafter, the Project) is located on Nanpanjiang River on the boundary of Luxi County and Qiubei County, Yunnan Province, People’s Republic of China. The Project is developed by China Resource Power Yunnan Honghe Company Limited(hereafter, the Project Owner). The purpose of the Project is to utilize the hydro resource to generate electricity which would otherwise have been produced by fossil fuel-fired power plants.
The Project is a dam-toe type hydropower station. The total installed capacity is 210MW (3*70MW), and the annual electricity generation is 803,500MWh. The electricity will supply the Yunnan province power grid and finally connect to the China Southern Power Grid (hereafter referred to as CSPG). The Project is expected to reduce emissions of greenhouse gases by an estimated 700,009tCO2e per year during the first crediting period. Without the CERs revenue, the Project cannot be realized because of the lack of profitability.
For the Project,
(a) The scenario existing prior to the start of the implementation of the project activity is CSPG
providing the same electricity service as the Project; (b) The project scenario is the implementation of the Project, the installation and operation of 3 sets of
turbines with a total capacity of 210MW which will supply an average annual generation of 803,500 MWh to CSPG and replace the same amount of electricity generated by fossil fuel fired power plants connected to CSPG;
(c) The baseline scenario is the same as the scenario existing prior to the start of implementation of the
project activity.
As a renewable energy project, the Project will produce positive environmental and economic benefits and contribute to the local sustainable development in comparison to other fossil-fuel (mainly coal) power generation. The specific sustainable development benefits of the Project are listed as follows:
• To displace a part of the electricity from coal-fired power plants, and thus will avoid environmental pollution caused by coal burning;
• To make good use of the local water resource to solve the difficulties of power shortage and voltage stability, improve the life quality of local people and reduce poverty; • To increase job opportunities: the Project will employ 123 persons during the project operation phase; • To increase tax income for local government.
CDM – Executive Board
These contributions are reaffirmed by the stakeholder consultation in section E. The project has received 100% support from local people. As for the environmental impacts arising from the project, they are primarily temporary and can be effectively mitigated through measures specified in the EIA report, hence considered to be insignificant.
Another issue which is of much concern for a hydropower project is migration and resettlement. The project involves migration of 481 inhabitants. All migrants have been resettled and compensated with subsidies, house and farmland etc. and are satisfied with the compensation plan.
Technicals
Investment
$154M
Energy
| Installed capacity | 210 MW |
| Effective hours | 3.83k h/year |
| Energy generated | 803.50k MWh/year |
| Utilization ratio | 43.68 % |
| Activity start date | - |
Time
In validation
: Total elapsed days between “opening comments” and the registration request date.In registration
: Total elapsed days from registration request until approval.To be registered
: Total elapsed days from Validation until Registration approval (Validation + Registration).To first issuance
: Total elapsed days from registration approval until first credit issuance.Total to first issuance
: Sum of entire validation, registration and ‘to first issuance’ days; i.e. the entire process.
| In validation | 207 days |
| In registration | 288 days |
| To be registered | 495 days |
| To first issuance | 301 days |
| Total to first issuance | 794 days |
Location
6 Organizations (7 roles involvement)
![]() | Participant name | Utility | PDD Consultant | () | China | Contact name |
![]() | Participant name | Certification | Validator | () | Japan | Contact name |
![]() | Participant name | Certification | Verifier | () | United Kingdom | Contact name |
![]() | Participant name | Certification | Verifier | () | United Kingdom | Contact name |
![]() | Participant name | Finance | Credit Buyer | () | Russia | Contact name |
![]() | Participant name | Carbon & Environment | Project Owner | () | China | Contact name |
![]() | Participant name | Other | Credit Buyer | () | Japan | Contact name |
This page has restricted access, it is only available to premium subscribers.
Need this information ? Sign-up for a premium account or buy the detailed report on this page.
Premium Account
Dedicated Reports
This page has restricted access, it is only available to premium subscribers.
Need this information ? Sign-up for a premium account or buy the detailed report on this page.
Premium Account
Dedicated Reports
This page has restricted access, it is only available to premium subscribers.
Need this information ? Sign-up for a premium account or buy the detailed report on this page.
Premium Account
Dedicated Reports
This page has restricted access, it is only available to premium subscribers.
Need this information ? Sign-up for a premium account or buy the detailed report on this page.
Premium Account
Dedicated Reports
This page has restricted access, it is only available to premium subscribers.
Need this information ? Sign-up for a premium account or buy the detailed report on this page.
Premium Account
Dedicated Reports
Similar Projects
Yunnan Kunming Dongchuan Xiaoqing River 7th Level Hydropower StationCDM | China | Issuance
Update : 2013-03-05 08:29:33
Dachunhe 50 MW Hydropower Project in Yunnan ProvinceCDM | China | Issuance
Update : 2013-03-15 16:49:08
Houpayan Hydropower Project in Qiubei County Yunnan Province, ChinaCDM | China | Issuance
Update : 2013-05-21 10:05:15
Sidehe 24.8MW Hydropower Project in Yunnan ProvinceCDM | China | Issuance
Update : 2013-05-21 12:04:35
Xiaopengzu 44MW Hydropower Project, Luquan County, Yunnan ProvinceCDM | China | Issuance
Update : 2013-02-01 05:48:52